3 189cf 9'x14' 1-2-4 (3/4') cement concrete columns R/F with
4 nos. of 3/8' bars strupps at 6" c/c (21 nos. columns
at 7'-0' c/c
525
99225
4 1050sf 6'x9' random bubble masonary work in 1:6 cement
sand motar
125
131250
5 350sgf Rubble work for foundation of 5' t/k and 2.5" width
with 4/1 wire mesh and 12x12 concrete
105
36750
6 800sf A wall on the same rubble work foundation 4'-0' height
and below 2'-0' width upwards 18" with stones according
to the taper and pont system
350
280000
7 210sgf To lay concrete on the top with 4/1" 3 wire and lay a
concrete layer of 4" according to the half round
sysyem
125
26250
8 Stone wall without plastering 15000
9 Two gate posts 4' -0' to lay a base under the ground
in the size of 6'-6' feet upward & 2'x8" to lay stones
in the center of the 2 posts 15000
10 Gate with the width of 14-0' 14'-0' to fix pipes & galvanized
iron higth 6'-0' 38000
TOTAL AMOUNT FOR THE PARAPET WALL 774615

St. Mary's Church - Beach Road Matara - Sri Lanka
The side boundry wall has been collesped and needs to be rebuilt
The length of this wall - 124 feet
Needs to be rebuilt up with 9" (thick) & 7'-0" in length
Cloumns of 4' wires have to be fixed
The Estimate for the wall :
744sf Excavation for the wal foundation
(2'-0') wide and 3'-0' height
13
9672
248sf 5' t/k 1-2-4 (3/4') cement concrete wall foundation. R/F
with 3/8" 4 steel bars at 9' in both ways
95
23560
153cf 9'x9' 1-2-4 (3/4) cement concrete columns R/F with
4 nos. of 3/8' bars and strupps of 6' C/C
475
72675
558sf Rubble work for wall foundation ( 18' wide & 3'-0' heigth)
135
75330
680sgf 9' thick brick work in 5'-6' height
135
91800
124cf The regin of the top with 4/1' 2 wires anf to lay concrete
of 5'tk
100
12400
1360sgf 1/2" tk 1.5 cement sand plastering to internal and
external face of the wall
35
47600
To fix a gate with pipe frame galvanized iron 5'-0'
height 4'-6' width 6000
TOTAL AMOUNT FOR THE BOUNDRY WALL 339037
 

Wood Mahogany

A. 11 Nos. fix doors

88 x 44 @ 14,000 = 154,000

B. 24 Nos. top doors with glasses

88 x 24 @ 7000 = 168,000

C. 01 Number main Door (Parlor)

87 x 42 = 17,250

Total = 339250

I will supply these to the wood fit the glasses with linges and latches to spray painted. Transport free of charge

W. Lal Fernando, Moratuwa Tel. 011-2650512

SHRINE OF OUR LADY OF MATARA
Reconstruction of the Groto
Discription Qty: Rate Total
1.Excavetion for Foundation Trenches 100 12/= 1,200.00
2.Plain concrete GR.15 in 3 thick concrete layer under rubble foundation.      
85 40/= 3,400.00
3.Random rubble masonry work 84 110/= 9,290.00
4.3'-0' x 3'-0' 1.2.4 (3/4)Cement concrete column base. 4 400/= 1,600.00
12'x12columns R/F with 4 Nos of 1/2" bars. 52 600/= 31,200.00
5.Calicut tiles roofing frame out with all timber. 250 300/= 75,000.00
6.Rubble work.(3'-6" x 3'-6" x 3'-0") 30 200/= 6,000.00
7.Concrete for floor. 121 90/= 10,890.00
8.Plastering and hand rail     7,000.00
9.Fix in Statue       4,500.00
     
Total               150,080.00

SHRINE OF OUR LADY OF MATARA
Estimate for the Repairs for the Roof of the Church
Discription Qty: Rate Total
1.Remove excisting Rafters &Calicut Tiles.     15,000.00
2.Inclined timber ceiling (Lunumidella) Rate shall include for polishing &apply wood preservative.      
7900 250/= 197,500.00
3.Fix in Valance board 458 160/= 73,280.00
4.Fix in Gutters 458 130/= 59,540.00
5.Fix in down pipe 230 110/= 25,300.00
       
Total     370,620.00

SHRINE OF OUR LADY OF MATARA
Parapet wall behind the mission house
Discription Qty: Rate Total
Excavatiobn for foundation trenches 450 12/= 5,400.00
Plain concrete Gr: 15 max aggregate size 3/4 " x 3" thick concrete layer under rubble foundation      
180 40/= 7,200.00
Raydom rubble masonary in lis cement mortas 115 90/= 10,350.00
8''+4'' 1.2.4. (3/4) cement concrete columns R/F with 2 Nos.      
0810 mm bars 220 95/= 20,900.00
Block work (5'-0'' height) 1250 64/= 80,000.00
4''+4'' cement concrete on wall top level R/F with 2 nos of 4/1'' bars 250 95/= 23,750.00
Internal and external plaster to wll finish rough 2500 30/= 75,000.00
Total     222,600.00